Here’s a detailed timeline for registration of International Non-Governmental Organizations (INGOs) in Pakistan:
Pre-Application (Weeks 1-4)
1. Research and planning: 2 weeks
2. Prepare documents: 2 weeks (Constitution, Articles, Bylaws, etc.)
3. Designate local representative: 1 week
4. Gather additional information: 1 week (project proposal, budget, etc.)
Application Submission (Weeks 5-8)
1. Submit application: 1 week (online or in-person)
2. Pay registration fee: 1 week (PKR 50,000 to PKR 100,000)
3. Provide additional information: 2 weeks (if required)
Verification and Background Check (Weeks 9-16)
1. Verification of documents: 4 weeks
2. Background check: 4 weeks (organization and representatives)
3. Security clearance: 4 weeks (if required)
Registration Approval (Weeks 17-24)
1. Registration approval: 4 weeks
2. Issuance of registration certificate: 2 weeks
Renewal and Updation (Annually)
1. Renewal application: 2 weeks (before expiration date)
2. Update certificate: 2 weeks (if address or details change)
Total Duration
– Registration process: 7-15 months
– Renewal process: 2-4 months
Key Milestones
1. Application submission: 1-3 months
2. Verification and background check: 3-6 months
3. Registration approval: 3-6 months
4. Registration issuance: 2 weeks
Contact Information
– Ministry of Interior, Government of Pakistan
– Phone: +92 91 9200535
– Email: info@interior.gov.pk
– National Database and Registration Authority (NADRA)
– Phone: +92 91 9221333
– Email: info@nadra.gov.pk
Please note that the timeline may vary depending on the complexity of the application and the efficiency of the authorities. It’s essential to consult the Ministry of Interior’s website or contact relevant authorities for the most up-to-date information.